Material change diagram with a drawing, a data sheet and an approval record.
Material SelectionNovember 26, 2026

How to Evaluate a PEEK Alternative for a Drawing

Identify the original PEEK grade, compare evidence under relevant conditions and record who can approve a material substitution.

If a drawing specifies a PEEK grade, treat a proposed alternative as a change that needs review. Identify the original reference and the requirements it meets. Compare the candidate using data under relevant conditions and take the evidence to the person who can authorize the change. The goal is to preserve the part’s function and keep a traceable decision.

Identify the reference that controls the order

Look for the grade and manufacturer on the drawing, bill of materials or purchase specification. Record the revision, supplied form and any requirements for reinforcement, electrical behavior or lot documents. If the drawing and purchase order disagree, ask the design owner which governs before requesting an alternative.

Compare evidence that matters for the part

How to review an alternative to specified PEEK
QuestionHow to document it
Will it serve the same function?Identify the requirement driving the design, such as deflection under load, contact wear or an electrical property.
Are the data comparable?Check the method, temperature, specimen orientation and form tested. Ask for additional evidence or define a test if data are missing.
Can it be made and verified?Confirm the stock form and dimensions. If the change may affect machining or fit, plan a trial with acceptance criteria.

Victrex 450G is a general-purpose grade. Victrex 450GL30 contains 30% glass fiber. The example shows why the full code matters. The polymer family and color alone leave out formulation differences. For a machined part, ask for data on the plate or rod being offered and check how those data relate to resin properties.

Record the decision before changing the order

Prepare a short comparison of the original and candidate, accepted data, unresolved items, test results if needed, and the approver. Retain the drawing revision and any lot or application restrictions. While engineering approval is pending, keep the request for the original grade separate from the proposed alternative.

An example of keeping alternatives separate

Suppose purchasing receives two proposals for PEEK plate. One matches the drawing grade and the other uses a reinforced grade. Keep both references separate. If two holes must stay aligned as the part heats up, ask for expansion data along that dimension and define how hole spacing will be measured on a trial part. If an alternative fails a mandatory requirement, record the reason so the same proposal does not return to the order without new evidence.

See PEEK in the catalog or the guide to requirements for PEEK, PAI and PEI. To request a material quote, share the original grade, shape, dimensions, quantity, delivery city and whether alternatives may be evaluated.

Frequently asked questions

What if the grade on the drawing has been discontinued?

Ask the manufacturer or supplier for the successor reference and its data sheet. Give that evidence to engineering to decide whether testing or a drawing revision is required.

Can a quotation authorize the change?

A quote identifies the proposed supply. The person with design authority or the customer records acceptance under the applicable process.

What goes in the request if alternatives are allowed?

Give the original grade and the mandatory properties or documents. Ask the supplier to identify each alternative separately by manufacturer, grade and supplied form.